Home  >  Accomplishments  >  ACCOMPLISHMENTS

ACCOMPLISHMENTS

No. Project Period Client/Country
84 [Transmission & Substation] Electrical Design of 154kV Cogeneration Substation at STX Energy in Banwol Aug 2013 - Oct 2014 LS Industrial Systems
83 [Transmission & Substation] Supervision and Inspection of 345kV Shinulsan - Shinonsan Underground Transmission Line Construction Aug 2013 - Aug 2014 KEPCO
82 [Transmission & Substation] Electrical Design of 345kV Transmission Line and Switching Station at Cheongsong Wind Power Plant May 2013 - Mar 2015 Cheongsong Wind Power
81 [Transmission & Substation] Supervision and Inspection of Shunt Reactor at 345kV Shin-gimpo Substation April 2013 - Aug 2013 KEPCO
80 [Transmission & Substation] Electrical Design of 154kV Substation at LG Electronics Pyeongtaek Factory May 2011 - Oct 2011 LS Industrial Systems
79 [Transmission & Substation] Supervision and Inspection of 154kV Substation Construction at Seoul Semiconductor Ansan Plant Dec 2010 - April 2011 Seoul Semiconductor
78 [Transmission & Substation] Electrical Design of 154kV Substation at LG Display Factory in Paju Oct 2010 - Feb 2011 LS Industrial Systems
77 [Transmission & Substation] Technology Service for 154kV Power Receiving Facility at LS Nikko Copper Smelter Sept 2010 - Dec 2010 LS Industrial Systems
76 [Transmission & Substation] Transmission Line Electrical Design and Design Standards Preparation at Gori Nuclear Power Plants 1 July 2010 - July 2011 KMENT
75 [Transmission & Substation] Supervision and Inspection of Cable Head Construction for 345 kV Dong-seoul Transmission Line in Tanbeol July 2010 - Mar 2011 Ina Construction
74 [Transmission & Substation] Electrical Design of 154kV Daesung Industrial Gas Substation in Yeochun Nov 2009 - May 2011 LS Industrial Systems
73 [Transmission & Substation] Basic Electrical Design for Transmission Line Relocation in Seoul Sept 2009 - Dec 2009 LH
72 [Transmission & Substation] Supervision and Inspection for Transmission Tower Relocation on 154 kV Dongsu Transmission Line Sept 2008 - Feb 2010 RDM
71 [Transmission & Substation] Basic Electrical Design of Underground Transmission Line in Paju Aug 2008 - Sept 2008 Dohwa Construction
70 [Transmission & Substation] Supervision and Inspection of Transformer Installation at 345kV Gunsan Substation June 2008 - Mar 2009 KEPCO
69 [Transmission & Substation] Electrical Design of 345kV Sintangjeong Substation May 2008 - Oct 2009 Samsung Engineering
68 [Transmission & Substation] Electric Design of 154kV AFK Substation in Gumi Mar 2008 - May 2008 LS Industrial System
67 [Transmission & Substation] Establishment of Substation Information Management System Jan 2008 - Feb 2008 Seondo Soft
66 [Transmission & Substation] Electrical Design of 154kV Substation at Siltron Plant 3 June 2007 - Nov 2007 LS Industrial Systems
65 [Transmission & Substation] Electrical Design for 345kV Shin-sungnam Transmission Tower Relocation June 2007 - Sept 2007 KEPCO
  1 / 2 / 3 / 4 / 5 / 6 / 7 / 8 / 9 / 10 /